Garage for Model T

Funding

Budget Expenditures
Encumbrances Budget Remaining
Fiscal Year 13-14
$135,000
$10,368


Fiscal Year 14-15

$3,625
$5,175

Total
$135,000
$13,993
$5,175
$115,832

Project Description
This project would fund the design and construction of an enclosed garage that would house a historic Model T car.  The structure would include a concrete pad, metal building, and automatic door.  The Hotel Motel Fund is funding this project. 

Future Operating Impact

Maintenance costs of the garage will be minimal, as will be the associated utility costs.  Additional costs may be approximately $1,200 annually. 

First Quarter FY 14-15
The Architectural Design for the Model T Garage is about 80% complete.  I am currently in contact with Ray Hollington Architects, Inc, to provide them with the remaining design criteria.  We are expecting the design to be 100% completed in the next quarter. 

Second Quarter FY 14-15
As of 3/26/15, we have started the bidding process with purchasing to obtain bids for construction of the project.  Currently we are still building the bid paperwork, once this is complete, the project will go out for bid.  Construction will commence once a contractor is selected.