Funding
Fiscal Year 12-13
|
$125,000
|
|
|
|
Fiscal Year 13-14
|
|
|
|
|
Fiscal Year 14-15
|
|
|
$5,520
|
|
Total
|
$125,000
|
|
$5,520
|
$119,480
|
Project Description
This project provides for the construction of a parking lot at 113 S. 3rd Street. Parking along Main Street has been an issue for many years and this lot will provide much needed public parking for patrons to the businesses located from 5th Street to Broadway along Main Street. The project will be funded by an Economic Development Fund transfer.
First Quarter FY 14-15
Parking Lot will be constructed after 3rd Street Drainage improvements completed.
Second Quarter FY 14-15
Parking lot will be let in second quarter and is estimated at approximately $84,000.00