Funding
Fiscal Year 13-14
|
$150,000
|
$49,432
|
|
|
Fiscal Year 14-15
|
|
$61,461
|
$49,973
|
|
Total
|
$150,000
|
$110,893
|
$49,973
|
($10,866)
|
NOTE: This project does not roll forward each year. A new amount is budgeted each year.
Project Description
These funds will be used to repair sidewalks located in various parts of the City. This is the Thirteenth year of a program designed to replace badly deteriorated sidewalks. The sidewalks to be improved will be selected using guidelines previously reviewed and approved by Council.
First Quarter FY 14-15
Project to be complete by February 2015. Approximately 1200 linear feet remaining to be replaced.
Second Quarter FY 14-15
On going project nearing completion. Second Quarter sidewalk project being designed and will be let.