The drainage improvement project is intended to be an ongoing, annual project that incorporates maintenance of existing facilities, investigates and designs improvements to provide relief to specific areas, and provides for contract design and construction of identified improvements beyond the scope of City capabilities.
First Quarter FY 14-15
Awarded slope paving construction of the West D Street outfall at Hwy 146 to Brooks Concrete Construction.
In-house forces working on drainage maintenance on the Northeast side.
Second Quarter FY 14-15
Completed slope paving the West D Street outfall at 146.
In-house forces working on drainage maintenance on the Northeast side. Installed approximately 200 feet of storm sewer, inlets and sidewalk in the 900 Block of South Kansas.
Budget | Expenditures |
Encumbrances | Budget Remaining |
|
---|---|---|---|---|
Fiscal Year 09-10 |
$144,000 |
|||
Fiscal Year 10-11 |
$270,000 |
$409,664 |
||
Fiscal Year 11-12 |
$195,000 |
$63,533 |
||
Fiscal Year 12-13 |
$250,000 |
$74,523 |
||
Fiscal Year 13-14 |
$220,000 | $75,163 | ||
Fiscal Year 14-15 |
$240,000 | $108,939 | $31,605 | |
Total |
$1,319,000 | $731,821 | $61,305 | $555,574 |
Project Description
The drainage improvement project is intended to be an ongoing, annual project that incorporates maintenance of existing facilities, investigates and designs improvements to provide relief to specific areas, and provides for contract design and construction of identified improvements beyond the scope of City capabilities.
First Quarter FY 14-15
Awarded slope paving construction of the West D Street outfall at Hwy 146 to Brooks Concrete Construction.
In-house forces working on drainage maintenance on the Northeast side.
Second Quarter FY 14-15
Completed slope paving the West D Street outfall at 146.
In-house forces working on drainage maintenance on the Northeast side. Installed approximately 200 feet of storm sewer, inlets and sidewalk in the 900 Block of South Kansas.